Details:

Study, installation, and commissioning of two thermal power transmission systems of 45 MWth per unit, from the already installed gas-to-water heat exchangers of units I and II to the already installed energy recovery systems from the exhaust gases of units III and IV for preheating the condensate in units III and IV, respectively.

Works executed:

Assembly and welding of pipelines, construction of new piping systems – isolation network for unit IV of Agios Dimitrios TPP.