Project information
Details:
Detailed design, procurement, and construction for the 2nd upgrade of the cryogenic facilities at the LNG terminal on Revythousa Island – pipeline and equipment erection works.
Works executed:
- Assembly and welding of ducts, construction of new pipelines.
- Existing building area on Revythousa Island.
Installation of cryogenic supports.
- Revythousa
- 16/1/2018 - 2/6/2018