Thermal Power Transmission Systems

Pictures

Project information

Details:

Agios Dimitrios TPP – study, supply, installation, and commissioning of two thermal power transmission systems of 45 MWth per unit, from the already installed gas-to-water heat exchangers of units I and II to the already installed energy recovery systems from the exhaust gases of units III and IV for preheating the condensate in units III and IV, respectively.

Works executed:

  • Assembly and welding of ducts, construction of new pipelines.
  • Existing building area
    2nd area inside the boiler (pressure pumps) – energy balancing
  • Sections in the BANKER HOUSE at the specified level